A small project has 7 activities and the time in days for each activity is given below:
Activity Duration in Days
A 6
B 8
C 3
D 4
E 6
F 10
G 3
• Given that activities A and B can start at the beginning of the project. • When A is completed C and D can start. • E can start only when B and D are finished. • F can start when B, C and D are completed and is the final activity. • G can start when E is finished and is the final activity. Draw the network diagram, determine the critical path, and calculate the project completion?